A Business Guide to the Great British Grid

5 mins read

Updated: null

Understand the new Great British Grid initiative, what it means for business electricity connections, and how it aims to cut costs and delays.

A Business Guide to the Great British Grid

Compare energy prices

The UK government has announced a major initiative to modernise the country’s electricity network: the Great British Grid. For businesses, this signals significant changes to how they connect to power, how much it costs, and how quickly they can get it.

Grid connections have become a serious bottleneck for British businesses, with some firms waiting years to get the power they need to expand, decarbonise, or build new premises. The recent energy crisis highlighted the volatility of energy costs, and whilst wholesale prices have eased since their peak, the underlying challenges of an ageing infrastructure remain. This guide explains what the Great British Grid is, why it’s needed, and what it means for your company’s energy plans.

Average Trend in UK Electricity Prices

5p10p15p20p25p200420062008201020122014201620182020202220242026Pence per kWh
Average

Average fully delivered prices: standing charges and all other non-VAT costs are included in the per-unit figure, so these are not directly comparable with the unit rate on a quote.

What Is the Great British Grid?

The Great British Grid is a new, publicly owned body created to accelerate the upgrade of the UK’s electricity network. Announced in September 2026, it is part of the government-backed Great British Energy and will be tasked with investing in the grid infrastructure needed to power Britain’s homes and businesses.

It is not a nationalisation of the entire grid. Instead, Great British Grid will work alongside existing private network operators and investors, using public money to speed up critical projects and increase competition. It will complement the work of existing bodies, including:

  • Ofgem - The independent energy regulator.

  • National Energy System Operator (NESO) - Responsible for planning and coordinating the electricity system.

  • Distribution Network Operators (DNOs) - The regional companies that own and operate the local electricity wires.

Think of it as a state-backed investment and delivery partner, designed to unblock delays and ensure the grid can handle the demands of a modern economy.

Why Is a New Grid Body Needed?

For years, getting a new or upgraded electricity connection has been a source of frustration for businesses. The system is congested, and the infrastructure is ageing. The creation of the Great British Grid is a direct response to several key challenges.

The Connection Queue Crisis

Any business that needs a new connection joins a queue. This queue has become exceptionally long, with over 700 GW of projects waiting for a slot - far more than the grid can handle. Many of these are speculative “zombie projects” that may never be built but hold capacity, blocking viable businesses from getting connected. Reforms are already underway to tackle this, with the government, Ofgem and the National Energy System Operator having removed over 300 GW of speculative projects from the queue to prioritise those that are ready to go.

The Need for Modern Infrastructure

Britain’s electricity grid needs to be expanded and modernised at an unprecedented pace. Demand is rising as businesses electrify their vehicle fleets, install heat pumps, and adopt new technologies. The growth of renewable energy also requires a grid that can handle power flowing from millions of smaller generators, not just a few large power stations.

This requires huge investment. NESO has estimated that around £89 billion will be needed throughout the 2030s to upgrade and modernise the grid. The Great British Grid is intended to act as a catalyst for this investment, bringing public capital to the table to speed things up.

How Will the Great British Grid Affect My Business?

The primary goal of the Great British Grid is to make it faster and cheaper for businesses to get the electricity connections they need. It plans to achieve this in four main ways:

  1. Accelerating Connections: By investing in infrastructure and clearing bottlenecks, the initiative aims to significantly reduce the multi-year waits that many businesses currently face.

  2. Increasing Competition: Great British Grid will be able to compete with established network companies to deliver new transmission projects. This is intended to drive down costs, improve service, and encourage innovation.

  3. Lowering Costs: Faster connections and more competition should lead to lower overall costs for businesses needing a new supply.

  4. Supporting Self-Build Connections: The government is expanding the rights of businesses to build their own connections. Great British Grid will be able to co-invest in these projects, giving companies more control over their timelines and costs. This approach has proven successful in Ireland, where it has reduced connection times by up to 11 months.

A Practical Guide to Getting a New Electricity Connection

Whilst the Great British Grid will shape the future, businesses needing a connection today still have to navigate the current system. The process involves several key players and steps, which we cover in more detail in our ‘A Guide to Commercial Electricity Meter Installation’.

Step 1: Determine Your Requirements

Before you apply, you need a clear picture of your needs. This includes:

  • Site Plans: A detailed plan of your premises, showing where the connection is needed.

  • Load Requirement: The maximum amount of power you will need, measured in kilovolt-amps (kVA). This is critical and should account for future growth, such as installing EV chargers or electrifying heating.

  • Annual Consumption: An estimate of your total electricity usage in kilowatt-hours (kWh) per year.

Step 2: Apply to Your Distribution Network Operator (DNO)

The process starts with an application to your regional DNO, the company that runs the local electricity network. There are six major DNOs in Great Britain, and you can find yours by entering your postcode on the Energy Network Association’s website. The DNO will assess your application and provide a formal connection offer.

Step 3: Consider an Independent Connection Provider (ICP)

You do not have to use your DNO for all the work. For many parts of the project - known as “contestable works” - you can hire an Independent Connection Provider (ICP). ICPs are accredited companies that can design and build your connection, often more quickly and cheaply than the DNO.

The final connection to the live network, known as “non-contestable works,” must still be done by the DNO. Using an ICP gives you a choice and can be particularly useful for a “self-build” connection, where you manage the project yourself.

Step 4: Appoint an Energy Supplier

This is a crucial step that many businesses miss. You must have a contract with a licensed business energy supplier before your meter can be installed and your connection made live. If you don’t have a supplier lined up, your connection will be delayed. You should start comparing suppliers as soon as you have a confirmed connection date from your DNO or ICP.

How Does This Fit with Great British Energy?

Great British Energy and Great British Grid are two sides of the same coin, a policy detailed in our ‘A Guide to Labour's GB Energy’.

  • Great British Energy is a publicly owned company that invests in developing clean energy generation projects, like wind and solar farms, and their supply chains.

  • Great British Grid is a body within Great British Energy that will focus on the infrastructure - the poles, wires, and substations - needed to get that clean energy from where it’s made to where it’s used.

Together, they are designed to manage the end-to-end process, from generating clean power to delivering it to businesses and homes. Great British Grid will have access to Great British Energy’s £4 billion investment fund to help it deliver on its goals.

What Happens Next?

The creation of Great British Grid is part of a wider programme of reforms. In the coming months and years, you can expect to see:

  • New Ofgem Rules: The regulator is overhauling the connections process. Its “Connect and Manage” reforms are specifically focused on making it easier for businesses to self-build their own connections.

  • Action on Speculative Projects: Ofgem is introducing measures like a “Data Centre Commitment Fee” to stop speculative projects from blocking the queue.

  • More Competitive Tendering: The process for awarding contracts for major grid projects will be opened up to more competition, with Great British Grid able to bid.

The initial start-up costs for Great British Grid will be covered by Great British Energy's existing budget, with long-term funding to be determined in a future government spending review.

Frequently Asked Questions

How Much Does a New Business Electricity Connection Cost?

Costs vary widely depending on the scale of the work. Indicative figures suggest a small business connection for a shop or small office could be £1,500 - £3,000, whilst a small industrial unit might be £4,000 - £15,000. Large sites requiring a new substation can cost tens of thousands of pounds or more. National Grid suggests a typical small business connection costs around £6,000. The final price depends on the distance from the existing network, whether roads need to be excavated, and if the local grid needs reinforcing.

How Long Does a New Connection Take?

Timelines can range from a few weeks to over two years for very large projects. A connection for a commercial property could take 12-26 weeks after the quote has been accepted and paid for. Delays in the queue have historically pushed these timelines out much further, which is what the new reforms aim to fix.

How Do I Apply for Support from Great British Grid?

This is not yet clear. The government has announced that Great British Grid will be able to co-invest in projects, particularly self-build connections, but the mechanism and eligibility criteria for businesses to apply for this funding have not been published.

What Is the Difference Between a DNO and an IDNO?

A Distribution Network Operator (DNO) is the regional monopoly responsible for the existing local network. An Independent Distribution Network Operator (IDNO) is a licensed company that can own and operate new extensions to the grid, often built by an ICP. For a business, the key difference is that you must use your regional DNO for some services, but you can choose to work with an ICP and an IDNO for a more competitive and flexible connection process.

Getting Your Business Ready for the Future

The Great British Grid represents a long-overdue overhaul of the UK’s energy backbone. For businesses, it promises a future of faster, cheaper, and more reliable access to the power needed for growth and decarbonisation. Staying informed about these changes will be key to planning future projects and managing your energy strategy effectively.

Compare energy prices


Related Guides & Tools

A Guide to Labour's GB Energy

A Guide to Labour's GB Energy

Discover Labour's GB Energy plan in our guide. Learn how it aims to transform the UK energy sector, boost sustainability, and provide affordable power for all.

What is the National Grid? A Complete Guide

What is the National Grid? A Complete Guide

Learn about the National Grid with our comprehensive guide. Find out how it powers your daily life and its impact on the energy landscape.

A Guide to Commercial Electricity Meter Installation

A Guide to Commercial Electricity Meter Installation

Learn about commercial electricity meter installation: the process, benefits for your business, and how the right meter can reduce energy costs.

Guides

© Switch Pal Limited 2026

All rights reserved. Switch Pal Limited is registered in England & Wales: 12545529

Registered address: 66 Paul Street, London, EC2A 4NA

Made with 💜 in London, UK